DISRUPTION 

Tuesday’s disruption was announced by SBS Transit at around 11.30am, stating that train services between Farrer Park and Punggol Coast MRT stations on the NEL and the entire Sengkang-Punggol LRT were affected. 

Power was progressively restored to the affected stations, and NEL services fully resumed at 2.10pm.

However, services on the Sengkang-Punggol LRT were down for about five hours. 

SBS Transit Group CEO Jeffrey Sim said that recovery works for the LRT service had to be carried out in stages to ensure a steady increase of the electrical load and prevent another power trip, as both the NEL and Sengkang-Punggol LRT were now relying on a shared substation. 

Power on the Sengkang LRT was restored at 3.34pm, while Punggol LRT had begun progressively resuming services from 4.15pm. 

However, to avoid stressing the power supply from the single substation, services on the Sengkang-Punggol LRT operated on a single track for both the east and west loops during the evening peak periods. 

Full services on the LRT were resumed as of 9.20pm. 

Acting Transport Minister Jeffrey Siow expressed disappointment last week at the rail disruptions in the last few months.

In July and August, services were disrupted on the East-West Line (EWL), Thomson-East Coast Line (TEL) and Bukit Panjang LRT. The EWL, TEL and Bukit Panjang LRT are operated by SMRT. 